Rebuild day 6

FamilyPosted by Jacob Sørensen Mon, January 15, 2007 21:42:38

At the end of day 6 insulation, floor heating tubes has been installed, and the cement has been poured. So now we have a rough floor.

Tomorrow the electrician will make power installation in the ceiling and the wall.

  • Comments(0)//blog.fasor.dk/#post18